Project cases

Work done on live pipes

Projects where shutting down was not an option.

6 / 6
Stainless ballast piping refit finished inside a dry-dock slot 2025
Marine · Singapore · 2025

Stainless ballast piping refit finished inside a dry-dock slot

A chemical tanker's ballast system was upgraded to 316L during a nine-day dry-docking. Cutting, beveling and fitting had to happen in a confined space with no hot work permit.

Read the case →
DN600 live main tapped overnight, no district shut down 2024
Water supply · China · 2024

DN600 live main tapped overnight, no district shut down

A new industrial park needed a 600 mm branch off the transmission main. Shutting the main meant cutting water to 12,000 households. We tapped it live, between 23:00 and 05:00, with a hydraulic machine and a mechanical tapping saddle.

Read the case →
PE gas line stopped and re-routed with no service interruption 2024
Gas distribution · Vietnam · 2024

PE gas line stopped and re-routed with no service interruption

A road widening project forced a DN315 PE medium-pressure gas line to move 9 meters. Rather than purge and re-commission the section, the contractor stopped the line live at both ends and tied in the new run.

Read the case →
Leaking 1970s cast iron main repaired without excavation 2024
District heating · Poland · 2024

Leaking 1970s cast iron main repaired without excavation

A 400 mm cast iron heating main under a tram line had three pinhole leaks. Excavation meant closing the street for a week. Two repair clamps and one night of work solved it.

Read the case →
Cooling water header modified during a 36-hour turnaround 2023
Oil & gas · Saudi Arabia · 2023

Cooling water header modified during a 36-hour turnaround

Six branch connections had to be added to a 24-inch cooling water header while the refinery kept running. Every item was pre-assembled and pressure-tested before the window opened.

Read the case →
Tailings line valve replaced at altitude, on a live line 2023
Mining · Chile · 2023

Tailings line valve replaced at altitude, on a live line

A 20-inch tailings line at 3,800 meters needed a failed knife gate valve replaced. Draining the line would have stopped the concentrator for two days.

Read the case →

Tell us the pipe, pressure and medium

Send the diameter, working pressure and what flows inside. We reply with a specification and price within one working day.