Stainless ballast piping refit finished inside a dry-dock slot
← All projects Marine · Singapore · 2025

Stainless ballast piping refit finished inside a dry-dock slot

A chemical tanker's ballast system was upgraded to 316L during a nine-day dry-docking. Cutting, beveling and fitting had to happen in a confined space with no hot work permit.

Ballast system upgrades on tankers are a sequencing problem as much as a fabrication one. The yard had nine days, four tank spaces and no permission to use a torch inside them.

We supplied split-frame cold cutting and beveling machines sized for 8 to 14 inch stainless, plus a portable power pack. The split frame allowed the machine to be mounted on pipe runs that could not be rotated or removed, and the cold cut left a bevel that passed the class surveyor's dye-penetrant check without rework.

All 26 cuts were completed in three shifts. The yard reported zero rework on bevels, which is what usually eats into a docking schedule.

26cold cuts
0bevel reworks
9 daysdock window met

Tell us the pipe, pressure and medium

Send the diameter, working pressure and what flows inside. We reply with a specification and price within one working day.

Send an inquiry →
WeChat Scan to add on WeChat JC-Leon
+86 18130056225